At the September Parish Council meeting GSPC agreed to commission a Feasibility Study into building a new car park and replacing the existing Memorial Hall. This follows on from initial ideas generated over the last nine months or so. The aim is to present the Feasibility Study to the village in April 2019, with enough detail to allow the Parish Council and village to proceed to a detailed design. Completion of the detailed design would then be the final checkpoint before deciding whether to go ahead with construction. The Terms of Reference for the Feasibility Study are here.
The project will potentially be of huge benefit to the village, but GSPC recognises it is also potentially high risk in terms of costs and disruption. By taking a phased approach we believe we can mitigate these risks and give everyone an opportunity to contribute to the project and review its viability before we commit to major expenditure.
Click here to see the terms of reference for the study.